SMITHFIELD STREET RECONSTRUCTION, PHASE II (TIP)
Pages 85–86 in Capital Budget · 2tables · includes narrative
SMITHFIELD STREET RECONSTRUCTION, PHASE II (TIP)
Functional Area: Engineering and Construction Project Type: New, Capital Project Responsible Department: DEPARTMENT OF MOBILITY AND INFRASTRUCTURE Project Manager: Deputy Director, Mobility and Infrastructure
Capital Improvement Program
Project Description
This project will reconstruct Smithfield Street from Forbes Ave. to Sixth Ave. Work will include reconstruction of the roadway, sidewalk, curb, street lighting, upgrades to two signalized intersections and to existing storm system, and new streetscape features.
Project Justification
Smithfield Street is a major thoroughfare in the Central Business District (CBD). The street has many businesses and transit stops. This project will upgrade Smithfield Street to current CBD Standards and for the consistency of CBD streetscape.
Shows capital project funding by source and year.
Operating Budget Impact
Staff time will be needed to manage vendor contracts and review plans. Operational maintenance will be necessary for any new features added to the streetscape or intersections.
Unexpended/Unencumbered Prior Year Funds $0
SMITHFIELD STREET RECONSTRUCTION, PHASE II (TIP)
2027 Deliverables and Objectives
Deliverables are tentative and subject to change Location

Lists project objectives, deliverables, and performance measures.
| Deliverable/Objective | Location | District | Fund | Cost |
|---|---|---|---|---|
| SMITHFIELD ST, PH. II - PRELIMINARY ENGINEERING | Smithfield St & Blvd of the Allies | District 6 | BOND | 180,000 |
| SMITHFIELD ST, PH. II - PRELIMINARY ENGINEERING (TIP) | Smithfield St & Blvd of the Allies | District 6 | OTHER | 720,000 |